BVE Update - September 13, 2012

Tender Released for BVE Improvements

This week we have tendered work on phase 1 and the wall reconstruction. This will include paving, curb/gutter and landscaping on the roadways and relocation/reconstruction of the marina walls.

It is expected that paving will be completed this fall, and landscaping completed in the spring.The wall will likely be completed this fall as well.

Phase 2 is in design and is expected to be added as extra work under the contract with completion by June 30 2013.

If you wish to view the specifics of the work to be completed, you can find all that information in the tender documents by clicking below:

Buffalo View Estates Tender Documents

 
BVE Update - August 15, 2012

Water & Sewer

There is a water system pressure test scheduled for Thursday.· For the most part,· residents will not know that the testing is happening, however, Residents can expect a short duration water outage from 10am - 2pm.· If all goes well, as the system performs well, all the work will be completed by 4pm.· If issues arise, time frames will be dependent on issues.

The sewer system inspection is complete and we are still waiting on the reports.

Mail Delivery

The County has been in contact with Canada Post trying to get mailboxes at Buffalo View Estates.  In a conversation with the Delivery Manager for our area, it was discovered that Canada Post is currently in the middle of a project that looks to standardize all mail delivery to a more urban-type delivery system.  They stated that until this project is complete, they will not be looking at adding anymore mail delivery units (ie. superboxes or rural mailboxes).  The County will continue to monitor Canada Post as they continue with this project and update residents accordingly.

 
BVE Update - August 3, 2012

As the long weekend approaches, there has been some activity at Buffalo View Estates.  Below is a brief update regarding the progress of Buffalo View Estates. 

If you have any questions about any of the work being done at Buffalo View Estates, plese don't hesitate to contact Tim Fox at 403-742-4441 or by email at This e-mail address is being protected from spambots. You need JavaScript enabled to view it .

Marina:

Alberta Sustainable Resource Development indicated they would like to see a design and restoration plan from the developer, then they would look at providing a field order to allow work to commence.

The developer have asked their engineer for a scope of work from their specialist for investigation, design and specifications related to getting approval of the work through SRD to their satisfaction. Any construction activities would be separate and based on output of investigation and SRD acceptance of design.